Bondwork Phase II

Our school is undergoing the second phase of bond-work construction this summer! Our hope is that all phases of construction will be completed when we return to school Fall 2024!

This summer’s work will include adding a secure vestibule to our main entrance (in blue above), moving the main office/workroom to a new location at our main entrance (in purple above), converting our current office/workroom into classrooms (in orange above), and some updates to our music room. Last summer, the work in green, yellow, and pink took place.

Our campus will be closed during constructions, so our office schedule and location will hop around during that time:

Bondwork Dates

    • June 15: Last Day Office is Open at Salem Heights
    • June 16-Sept 1: Salem Heights Campus Closed for Bond Work
    • June 20-23: Office working remotely, open for calls/emails
    • June 26: Salem Heights Office reopens at Schirle Elementary
    • June 29-Aug 4: Office Closed for the Summer
    • Aug 7-25: Salem Heights Office open at Schirle Elementary
    • Sept 5: Salem Heights Campus Reopens

Salem Heights Office staff will be relocating to Schirle Elementary during Construction.

We will still be able to receive phone calls at our normal number (503-399-3187), but visits from our families will need to take place at:

Schirle Elementary School

4875 Justice Way S, Salem, OR 97302

There will be signage near the entrance to direct you to our area.